Flood-Hit Areas: Power Restoration Progress Across Pakistan 2025
The Power Division reports that over 70% of flood-affected feeders across Pakistan have already been restored, with full recovery expected in several regions by early September 2025.
National Overview
Floods have damaged electricity infrastructure across multiple regions, but restoration work is in steady progress. Field teams from all distribution companies (DISCOs) are working around the clock to reconnect grids and feeders.
| Region (DISCO) | Grids Affected | Feeders Affected | Fully Restored | Partial/Temporary | Expected Full Restoration |
|---|---|---|---|---|---|
| PESCO (Swat, Buner, Shangla, Swabi, D I Khan) | 12 | 91 | 79 | 12 | Ongoing |
| GEPCO (Sialkot, Narowal, Wazirabad, Hafizabad) | 10 | 86 | 62 | 19 | Ongoing |
| LESCO (Lahore, Kasur, Okara) | — | 46 | — | 46 | Aug 31–Sep 1, 2025 |
| FESCO (Chiniot, Jhang, Sargodha, Mianwali, D I Khan) | 15 | 43 | Temporary | — | Ongoing |
| MEPCO (Multan region) | 11 | 63 | — | — | Once floodwaters recede |
| TESCO (North Waziristan) | — | 2 | Temporary | — | Sep 5, 2025 |

Power Restoration in PESCO Region (Khyber Pakhtunkhwa)
In Swat, Buner, Shangla, Swabi, and D I Khan, 12 grids and 91 feeders were damaged.
- 79 feeders are already restored.
- 12 feeders remain partially restored.
- Teams continue to repair high-voltage lines.
GEPCO Region (Punjab)
In Sialkot, Narowal, Wazirabad, and Hafizabad:
- 10 grids and 86 feeders were hit.
- 62 feeders fully restored.
- 19 feeders remain partially functional.
LESCO Region (Central Punjab)
Lahore, Kasur, and Okara saw 46 feeders disrupted.
- Partial supply restored across all LESCO feeders.
- Full restoration expected by Aug 31–Sep 1, 2025.
FESCO Region (Punjab)
Chiniot, Jhang, Sargodha, Mianwali, and D I Khan reported:
- 15 grids and 43 feeders down.
- Temporary power restored in most locations.
MEPCO Region (South Punjab)
Multan and surrounding areas were among the hardest hit.
- 11 grids and 63 feeders impacted.
- Restoration will begin once floodwaters recede.
TESCO Region (North Waziristan)
Two feeders in North Waziristan were downed by floods.
- Temporary restoration completed.
- Full restoration expected by Sep 5, 2025.
Key Takeaway
The Power Division assures that all regions will see complete restoration soon. Field teams are working continuously, and priority is being given to fully energize feeders serving hospitals, water supply systems, and emergency services.
FAQs
How many feeders have been restored in flood-hit areas of Pakistan?
Over 70% of affected feeders have been restored across multiple regions, with full restoration expected in early September 2025.
When will full power restoration be completed in LESCO’s region?
LESCO expects full restoration of 46 feeders in Lahore, Kasur, and Okara between August 31 and September 1, 2025.
Which region has the highest number of restored feeders so far?
The PESCO region leads with 79 out of 91 affected feeders fully restored across Swat, Buner, Shangla, Swabi, and D I Khan.
What is the status of power restoration in MEPCO areas?
In MEPCO’s region, 11 grids and 63 feeders were affected. Restoration will begin once floodwaters recede from Multan and surrounding areas.
Has temporary power been restored in FESCO-managed districts?
Yes, temporary restoration has been provided to 15 grids and 43 feeders in Chiniot, Jhang, Sargodha, Mianwali, and D I Khan.
What is the expected date of full restoration in TESCO’s region?
TESCO reports that full restoration of feeders in North Waziristan is expected by September 5, 2025.