Infographic showing the 5-step process for applying for net metering with LESCO, including application, document submission, site inspection, installation approval, and connection activation.

How to Apply for Net Metering with LESCO

What is Net Metering?

Net metering is a billing mechanism that allows consumers who generate electricity via solar panels to send excess power back to the grid. In return, the electricity utility, in this case, LESCO (Lahore Electric Supply Company) — credits their bill, effectively reducing monthly costs. So, it is necessary for every Lahore citizen to know how to apply for net metering with Lesco.

Net metering in Pakistan is regulated under NEPRA’s Distributed Generation and Net Metering Regulations 2015.

Eligibility Requirements for LESCO Net Metering

To qualify, you must meet the following:

  • Be a LESCO-registered consumer (residential, commercial, or industrial)
  • Have a solar PV system installed by a certified vendor (AEDB-approved)
  • The system capacity must be between 1kW and 1MW
  • You must use a bi-directional or smart meter capable of tracking imports/exports

Required Documents

Make sure to prepare the following:

  1. Copy of your latest LESCO electricity bill
  2. Ownership documents or tenancy agreement for your premises
  3. Solar system layout plan and single line diagram (approved by a certified engineer)
  4. NOC from AEDB-licensed installer
  5. Net metering application form (downloadable from LESCO’s DG Cell)

Tip: You can verify your LESCO consumer details via LESCO online bill check.

Illustration of a house with rooftop solar panels connected to LESCO’s power grid through a bi-directional meter, showing import and export energy arrows for net metering.

How to Apply for LESCO Net Metering? Step-by-Step Process

  • Install a solar PV system through an AEDB-approved installer
  • Submit application to LESCO’s DG (Distributed Generation) department
  • Site inspection by LESCO officials within 7–10 working days
  • Signing of Net Metering Agreement (valid for 3 years)
  • Bi-directional meter installation and commissioning
  • Activation and first billing with net metering adjustments

Net Metering Timeline with LESCO (Approx.)

StageTime Estimate
Site survey & inspection7–10 working days
Agreement & meter installation5–7 working days
Total application process2–3 weeks

NEPRA has recently mandated Discos to streamline net metering application timelines as per 2025 updates.

What Happens After Approval?

  • You will receive a Net Metered Bill, which shows both imported and exported units.
  • LESCO credits surplus energy sent back to the grid, reducing your monthly payable.
  • If exported energy exceeds imports, the credit is carried forward.

Common Mistakes to Avoid

  • Submitting incomplete documents
  • Installing unlicensed or non-certified systems
  • Not verifying if your meter is ToU-compatible

FAQs

Who is eligible to apply for net metering in LESCO?
Any LESCO consumer with a certified solar system between 1kW–1MW can apply.

How long does the LESCO net metering process take?
Typically 2–3 weeks from application to meter activation.

What happens to extra solar units generated?
They are credited on your bill and rolled over if unused.

Do I need a special meter for net metering?
Yes, a bi-directional or smart meter is required.

Where can I get the LESCO net metering application form?
From LESCO’s DG Cell or official LESCOl website.